环氧地坪漆施工前基础地面检查内容包括什么?

返回列表 来源: 浏览:212 发布日期:2019-7-31 9:20:54

环氧地坪漆对基础地面的平整度、含水率、地面强度要求比较高,直接关系着环氧地坪漆施工后的质量,如果地面不达标,就会出现起泡、脱层、起壳等现象。因此,施工环氧树脂地坪漆之前需要对基础地面进行检查,主要包括以下内容:1、地面平整度。可用2m直尺检查,记录间隙值,对地面过高初进行标记,一遍重点打磨,对过低初采用砂浆进行修补。2、基层含水率检查。首先向客户了解混凝土已养护时间,底层有没有施工防水层,在养护期间的天气状况等基本情况,并采用混凝土含税率测量仪对基材含水率进行测量,以便综合分析。

Epoxy floor paint has high requirements on the levelness, moisture content and strength of the foundation ground, which directly affects the quality of the epoxy floor paint after construction. If the ground does not meet the standard, foaming, delamination and shell will appear. Therefore, before the construction of epoxy floor paint, it is necessary to inspect the foundation ground, which mainly includes the following contents: 1. Flatness of the ground. It can be checked by 2m ruler to record the clearance value, mark the beginning of over-high ground, grind it once, and repair the beginning of over-low ground with mortar. 2. Inspection of moisture content in grass-roots units. Firstly, the customer is informed about the concrete curing time, whether there is a waterproof layer in the bottom layer, the weather condition during the curing period, and the moisture content of the base material is measured by the concrete tax rate measuring instrument for comprehensive analysis. 【测量重点采用如下原则选择】

[The key points of measurement are chosen according to the following principles]


①底层;

(1) Bottom layer;


②靠近门窗或外墙处;

(2) Close to doors and windows or outside walls;


③混凝土浇筑完工后积过水的地点。

(3) Places where water accumulates after concrete pouring is completed.


3、混凝土强度检查。主要检查混凝土表面是否由起砂现象,是否有空鼓现象,然后作好标记并记录。对强度较差的混凝土,处理时应特别注意,涂装前彻底吸尘后再用混凝土加强型底漆(利于渗透的底漆)大地,使之尽量深入渗透。局部空鼓应用灌浆料修补。

3. Strength inspection of concrete. Mainly check whether the concrete surface from the sand phenomenon, whether there is empty drum phenomenon, and then mark and record. For concrete with poor strength, special attention should be paid to the treatment. After thorough dust cleaning before painting, concrete reinforced primer (which is conducive to penetration) should be used to penetrate the ground as far as possible. Local empty drum is repaired with grouting material.


环氧树脂地坪漆施工步骤

Construction Procedures of Epoxy Resin Floor Paint


基础地面处理方法:

Ground treatment of foundation:


1、新竣工的工业环氧地坪必须经过一定的养护后方可施工,约28天。

1. The newly completed industrial floor must undergo certain maintenance before it can be constructed for about 28 days.


2、清除表面的水泥浮浆、旧漆以及粘附的垃圾杂物。

2. Remove surface cement slurry, old paint and adhering garbage and debris.


3、彻底清除表面的油污,用克油王清洗剂处理。

3. Clean up the oil stains on the surface thoroughly and treat them with Keyou King Cleaning Agent.


4、清除积水,并使潮处彻底干燥。

4. Clean up the stagnant water and dry the tides thoroughly.


5、表面的清洁需用无尘清扫机及大型吸尘器来完成。

5. Surface cleaning should be accomplished by a dust-free sweeper and a large vacuum cleaner.


6、平整的表面允许空隙为2~2.5mm,含水量在6%以下,PH值6~80。

6. The allowable voids on the flat surface are 2-2.5mm, the water content is less than 6%, and the PH value is 6-80.


7、环氧地坪表面的打毛,需用无尘打磨机来完成,并用吸尘器彻底清洁。

7. Ground surface polishing should be completed by a dust-free grinder and cleaned thoroughly with a vacuum cleaner.


8、对地坪表面的洞孔和明显凹陷处应用腻子来填补批刮,实干后,打磨吸尘。

8. Putty should be used to fill the holes and obvious depressions on the floor surface. After dry, it should be sanded and cleaned.